Deciding to redevelop a housing society is one of the most
critical decisions members and managing committees will ever undertake. On September
30, 2026, the Cooperation, Marketing and Textiles Department of Maharashtra
issued an updated Government Resolution (GR) under Section 79A of the
Maharashtra Co-operative Societies (MCS) Act, 1960.
This directive replaces previous frameworks (such as the
2019 guidelines) to bring complete transparency, curtail arbitrary committee
moves, eliminate builder favoritism, and protect flat owners. Below is an
end-to-end breakdown of what every housing society member in Maharashtra needs
to know.
1. Eligibility & Sole Decision-Making Authority
- Who
qualifies? Buildings declared dilapidated, ruinous, unsafe, or
dangerous (dhokhadayak) by a competent planning authority—such as
BMC, TMC, KDMC, NMMC, or MHADA—or those posing a threat to occupants,
adjacent structures, or road traffic are eligible. Redevelopment must
align with prevailing Development Control and Promotion Regulations (DCPR).
- Exclusive
Power with the General Body: The decision to enter redevelopment
belongs strictly to the housing society's general body. An
appointed administrator or an authorized registrar officer cannot
unilaterally initiate or decide redevelopment.
- Modes
covered: Self-redevelopment, developer/joint venture (JV) models,
single buildings, cluster redevelopment, and federation-led group
redevelopments.
2. Requisition, Timelines & The First SGM
- Initiating
the Process: At least 1/5th (20%) of the total registered members
must submit a formal requisition letter to a legally constituted, duly
elected Secretary.
- Managing
Committee Action: The Secretary must place this request before the
Managing Committee within 8 days. The committee must convene a
Special General Meeting (SGM) within 2 months of receiving the
requisition.
- Notices
& Inputs: An advance notice of 14 days along with the
meeting agenda must be delivered to each member. Members can submit
written suggestions, concerns, or architect/PMC recommendations up to 8
days before the SGM.
3. Quorum, Attendance & The 51% Voting Rule
A common misconception is that a redevelopment resolution
only needs a simple majority of members present in the room. The Section 79A GR
sets a far stricter bar:
- Quorum:
A minimum of 2/3rds (66.67%) of the total society membership must
be in attendance (rounded up to the nearest whole integer; e.g., 67 out of
100 members).
- Physical
Presence Mandate: While out-of-station or unwell members may
participate and vote via video conferencing/telecom channels, at least 51%
of the total society members must be physically present in the hall.
- 51%
of Total Membership: Approving redevelopment requires consent
from at least 51% of the society’s total registered strength, not
merely 51% of attendees. If a society has 100 members and 70 attend,
approval from at least 51 members is mandatory.
- Adjourned
Meeting Consequence: If the 2/3rd quorum is not met, the SGM is
adjourned and reconvened within one month with a 7-day notice. If the
adjourned meeting fails to reach the quorum again, the redevelopment
agenda is treated as rejected and cannot be reintroduced for 3 months.
- Written
Consent: A show of hands during the meeting is insufficient. All
consenting members must submit their approval in writing.
4. Appointing the Architect / PMC & Preparing the
Project Report
- Competitive
Selection: The Managing Committee must invite written bids/quotations
from at least three certified Architects or Project Management
Consultants (PMCs) empanelled with local planning bodies or the
Council of Architecture.
- Appointment:
The General Body selects one consultant during the SGM. An official
appointment letter must be issued within 30 days of the meeting.
- Comprehensive
Feasibility Report: Within 2 months of appointment, the
Architect/PMC must submit a Project Feasibility Report. This report must
evaluate:
- Complete
land title verification, conveyance deed status, and pending deemed
conveyance formalities.
- FSI,
permissible TDR, and incentive potential under relevant planning norms
(DCPR).
- Total
existing residential and commercial carpet area, required open
recreational spaces, and playground reservations.
- Multi-scenario
comparative options to enable an informed choice by the members.
5. Tendering & Developer Selection Rules
- Carpet
Area vs. Corpus Fund: Before floating the tender, the society—in
consultation with the PMC—must pre-fix either the minimum additional
carpet area or the minimum corpus fund. This prevents speculative or
distorted developer proposals and ensures fair, apples-to-apples bidding.
- Public
Tendering: Tenders must be published in widely circulated local
newspapers and placed visibly on the society notice board.
- Minimum
Bidder Requirement: A minimum of three competitive bids must be
received. If fewer than three bids arrive:
- The
submission window is extended by 15 days.
- If
still insufficient, a second extension of 7 days is given.
- If
three bids are still not received after both extensions, the society may
proceed to evaluate the available bids.
- Authorized
Registrar Officer: The final selection SGM for appointing the
developer must be held in the presence of an authorized representative
from the Cooperative Registrar's office.
6. Development Agreement (DA) & Permanent Alternate
Accommodation (PAAA)
- Execution
Timelines: Once the builder is approved by the General Body, the
formal Development Agreement (DA) must be executed within 3 months.
- Individual
PAAA: The developer must execute and register an individual Permanent
Alternate Accommodation Agreement (PAAA) with each eligible member.
- RERA
Carpet Area: All area allocations must explicitly reflect carpet area
defined under RERA regulations.
- Vacating
Safeguard: No builder can force members to vacate their homes until full
legal approvals (Intimation of Disapproval / Commencement Certificate) are
secured AND individual PAAAs are registered.
- Rent,
Deposit, and Transit Living: Developers must arrange either transit
camps or provide monthly rent (matched to prevailing local market rentals)
plus an upfront security deposit.
- Non-Transferability:
Development rights granted by the society are strictly non-transferable.
The developer cannot assign, sub-contract, or sell development rights to
third parties.
- Conflict
of Interest Bar: No Managing Committee member can act as the
developer, nor can any close relative of committee members participate as
the builder.
7. Crucial Additions Every Society Must Include
To ensure a secure redevelopment journey beyond statutory
minimums, societies should incorporate these industry-standard safeguards into
their agreements:
- MahaRERA
Registration: The new project must be registered on the MahaRERA
portal before marketing or booking sale-component flats.
- Irrevocable
Bank Guarantee: While the GR leaves the bank guarantee figure to the
General Body, societies should insist on a bank guarantee of at least
20% to 25% of the total construction cost from a scheduled bank, kept
valid until the Occupancy Certificate (OC) is issued.
- Strict
Construction Timelines: The DA must define a time-bound delivery
window (typically 24 months, with an absolute upper limit of 36 months
for unforeseen delays), accompanied by hefty per-day default penalties and
escalating monthly rent clauses.
- Escrow
Account Mechanism: Require an escrow account for construction
milestone funding and rent disbursement.
- Flat
Allocation Clarity: The General Body decides flat allocations with 14
days' notice. By default, allocations should maintain existing floor-wise
arrangements. If a lottery is unavoidable, it must be conducted only after
the structural work is completed.
- Video
Recording & Document Access: Every General Body meeting regarding
redevelopment must be video-recorded. Recordings and minutes must remain
accessible to all members, with copies filed with the Registrar within 14
days.
8. Penalties for Committee Misconduct & Protection
for New Buyers
- 6-Year
Disqualification: Under Section 79A(3) read with Section 78 of
the MCS Act, if committee members bypass guidelines, act
non-transparently, or commit irregularities, the Registrar holds the
authority to disqualify them from contesting or holding committee
office for 6 years. The Registrar can also supersede the committee and
appoint an administrative board.
- Mandatory
Membership for New Buyers (Point 13.5): Previously, buyers acquiring
flats from the developer's free-sale component faced resistance or
prolonged delays in getting admitted into the old housing society. Under
Clause 13.5 of the new GR, once possession is handed over, the existing
society must grant society membership and issue share certificates
within 3 months of application.
Key Redevelopment Milestones
|
Stage |
Key Milestone |
Statutory Timeline / Threshold |
|
Requisition |
Member Request for SGM |
Min. 1/5th (20%) of society members |
|
Notice |
SGM Notice & Agenda |
14 days prior notice |
|
Quorum |
Meeting Attendance |
2/3rds total members (51% physically present) |
|
Resolution |
Approval for Redevelopment |
At least 51% of total registered members |
|
Consultant |
PMC / Architect Appointment |
Letter issued within 30 days of SGM |
|
Feasibility |
Project Report Submission |
Within 2 months of PMC appointment |
|
Agreement |
Execution of DA with Builder |
Within 3 months of developer selection |
|
Protection |
Vacating Existing Flats |
Only after approvals in hand & PAAA registered |
|
New Buyers |
Society Membership & Share Certificate |
Within 3 months of application post-possession |