When real estate projects face delays, property buyers turn to MahaRERA to secure possession and claim delayed-possession interest under Section 18 of the RERA Act. Typically, penalties and fines are levied against developers. However, a significant ruling by MahaRERA reveals a procedural trap that can cost homebuyers a penalty instead.
Even if you bought multiple flats in the exact same tower from the exact same builder, filing a single "composite complaint" can cost you money and jeopardize your case.
The Case: Rajyog Corporations vs. Prashanti Land Developers
In an order passed on 12 October 2026 (Complaint No. CC12400317), MahaRERA dealt with a dispute involving two apartments (Flats 904 and 603) booked in the residential project "Rajhans" (MahaRERA Registration No.
P51900002771).- The Background: The complainant had executed two separate registered Agreements for Sale on 23 May 2018 with the original promoter, Pratham Developers. Full payment had already been disbursed by the buyer.
- The Delay: Possession was contractually promised on or before 30 June 2020. Later, on 6 November 2023, the project was transferred to Prashanti Land Developers Private Limited under Section 15 of RERA (transfer of promoter rights and liabilities).
- The Legal Action: Frustrated by prolonged handover delays, the buyer filed a single composite complaint before MahaRERA demanding immediate physical possession and statutory delayed interest for both flats.
What MahaRERA Ruled
While the Authority ultimately ruled in favor of the buyer—ordering the promoter to pay interest under Section 18 from 1 July 2020 until actual possession with an Occupancy Certificate (OC), along with ₹20,000 in litigation costs—it took strong exception to the way the petition was drafted.
MahaRERA ordered the complainant to pay a cost of ₹5,000 to the Authority.
The Core Legal Principle
Under the Real Estate (Regulation and Development) Act, 2016:
- Distinct Cause of Action: Each registered Agreement for Sale represents an independent contract and therefore constitutes a separate "cause of action."
- One Agreement = One Complaint: Regardless of whether the units are side-by-side, on adjacent floors, or belong to the same buyer under identical payment schedules, you cannot bundle them into one petition.
MahaRERA entertained the single complaint solely as a one-time exception to prevent further administrative hardship and multiple parallel proceedings for the buyer. However, the bench explicitly made it clear: this relaxation is an exception and cannot be cited as a legal precedent. To record this procedural breach, MahaRERA imposed the ₹5,000 cost on the homebuyer.
Crucial Lessons for Property Buyers and Investors
If you own or are planning to invest in multiple units within a single project, keep these procedural essentials in mind before approaching MahaRERA:
- File Independent Complaints: Always file a separate Form 'M' (Complaint) on the MahaRERA portal for each individual registered Agreement for Sale.
- Pay Individual Filing Fees: Every complaint requires its own mandatory filing fee (₹5,000 per complaint on the MahaRERA portal). Attempting to club two flats under one ₹5,000 filing fee is viewed procedurally as circumventing official registry fees.
- Section 15 Accountability: If a stalled project has been taken over by a new developer under Section 15 of RERA, the incoming promoter inherits the liabilities of the original promoter—including possession timelines and pending interest dues to existing allottees.
- Maintain Separate Document Trails: Ensure payment receipts, demand notes, and communication logs are filed neatly per unit. Bundled financial evidence complicates hearings and lengthens case scrutiny.
Key Takeaway
Getting your delayed possession interest shouldn't come with procedural fines. When dealing with regulatory bodies like MahaRERA, technical precision matters just as much as having a strong case. If you have purchased multiple units in a delayed project, treat each unit as an independent legal asset from day one.
For regular updates on property laws, RERA verdicts, and smart real estate investment guidance, stay connected with Gawe Realty.
Comments
Post a Comment